2007 February Report of the Auditor General of Canada
Exhibit 4—Transportation infrastructure projects: Summary analysis
|
Project |
Original target total cost |
Pre-tender construction cost estimates |
Lowest bid received |
Revised target total cost |
Management Board approval to increase target total cost |
Original expected completion date |
Substantial completion date |
Total costs incurred as of September 2006 |
Comments |
|---|---|---|---|---|---|---|---|---|---|
|
Teslin River Bridge Rehabilitation |
3,445,000 |
2,784,000 |
3,839,993 |
4,656,000 |
Yes |
15-Oct-04 |
15-Nov-05 |
4,479,757 |
The projects were funded under the Canada/Yukon Strategic Highway Infrastructure Program on a cost-share basis. |
|
Teslin River Bridge Phase 2—Pier 5 |
793,000 |
821,750 |
1,112,008 |
1,155,000 |
Yes |
30-June-05 |
10-Nov-05 |
1,192,526 | |
|
Takhini River Bridge Rehabilitation |
1,245,000 |
2,073,043 |
1,797,750 |
1,897,750 |
Yes |
15-Sep-05 |
1-Sep-06 |
1,846,208 | |
|
Old Crow Airport Runway and Electrical Upgrade |
2,956,000 |
1,650,000 |
2,781,750 |
3,656,000 |
Yes |
31-Mar-06 |
Ongoing |
3,152,697 |
Funding of up to $2,955,676 was provided from the federal Airports Capital Assistance Program. Funding of $700,000 was transferred from another project. |
|
Klondike Highway, |
2,750,000 |
2,100,000 |
2,246,680 |
3,150,000 |
Yes |
31-Aug-04 |
14-Oct-04 |
3,340,835 |
Funding of $400,000 was transferred from another project. Completion was targeted for July 2005 and achieved in April 2006. |
|
Alaska Highway, |
7,536,000 |
5,112,410 |
4,942,500 |
– |
– |
31-Aug-05 |
13-Oct-05 |
5,570,773 |
The projects are funded under the Canada Strategic Infrastructure Fund on a cost-share basis. |
|
Big Creek Bridge and Little Rancheria Bridge Deck Replacements |
1,572,000 |
1,130,760 |
1,234,000 |
– |
– |
30-June-05 |
13-Sep-05 |
1,598,288 | |
|
Teslin River Bridge Deck Replacement |
6,500,000 |
6,930,000 |
8,135,000 |
8,635,000 |
Yes |
30-Sep-07 |
Ongoing |
2,273,335 | |
|
Atlin Road, |
2,300,000 |
2,200,000 |
2,287,940 |
– |
– |
30-Sep-06 |
Ongoing |
999,591 |
The project was not justified according to the government directive, but Management Board granted exemption. |
|
Beaver Creek Airport Runway Resurfacing |
120,000 |
183,740 |
178,300 |
216,000 |
– |
31-July-05 |
20-Aug-05 |
202,572 |
Funds were transferred internally to cover cost increases. |
|
Alaska Highway, |
10,000,000 |
15,100,000 |
18,761,966 |
– |
– |
30-June-06 |
15-Mar-06 |
18,091,054 |
The projects are funded by the US government under the Shakwak Agreement between Canada and the United States. |
|
Donjek River Bridge Replacement |
25,000,000 |
28,251,300 |
34,936,500 |
34,937,000 |
Yes |
30-Sep-07 |
Ongoing |
24,171,024 | |
|
Yukon River Bridge at Dawson |
3,380,000 |
– |
– |
1,799,000 |
– |
– |
– |
1,611,817 |
The Government of Yukon decided to delay construction due to a heated construction market. |
Source: Department of Highways and Public Works