1998 April Report of the Auditor General of Canada
April 1998 Report—Chapter 1
Exhibit 1.4—Some of the Challenges or Difficulties Associated with
Program Review
-
A short time frame to submit proposals.
The time frame between the launch of
Program Review (May 1994) and the deadline for departments to submit their proposals
for expenditure reductions (August 1994) was short. Thus, there was not much time for
analyzing in detail the impact of what was proposed. Not all departments met the
deadline. The short time frame resulted in the final test, the "affordability test", being the
determining factor that drove proposals and eventually decisions.
-
Difficulties of setting fiscal targets at the portfolio level.
Fiscal targets for
ministerial portfolios were based on perceptions and the experience of central agency
personnel; there was no scientific basis for them. As a result, some could be challenged
or negotiated. Furthermore, significant differences in information available at the central
agency level compared with that available in departments led to at times lengthy and
arduous discussions about the numbers that were to be used as a base for making
expenditure reductions.
-
Departmental performance varied.
Departments that had launched their own
rethinking initiative prior to Program Review were generally better positioned to review
their programs within a strategic framework than those departments restructured in June
or November 1993. There were also differences in the way that departments applied the
six test questions, and the results were uneven, depending on several variables such as
the degree of commitment and involvement of departmental officials. Even if
departments were asked to look at programs and activities for a more strategic focus
and improved co-ordination and integration of programs and activities within their
portfolio, such strategic frameworks were generally not developed. There were no
specific criteria or predetermined performance indicators that could be used to
objectively evaluate the performance of departments.
-
Certain issues were not raised or not resolved.
The responsibility for raising
horizontal issues was left mostly with departments, the "centre" intervening only at the
request of ministers. Although a number of horizontal issues were raised, and some
resolved - such as the consolidation of responsibilities for food inspection - other issues
were not identified or could not be resolved, such as the presence of many government
departments in international affairs and in embassies, instead of a more centralized
approach. Certain functions or activities were not examined, such as the roles and
responsibilities of central agencies in relation to governance or to human resource
management.
-
Program Review II.
Although decisions stemming from Program Review I were not
revisited, the announcement of Program Review II soon after so much effort had been
devoted to meet the requirements of Program Review I had some negative effect. More
expenditure reductions were required and a 3.5 percent across-the-board cut was
imposed on departments and agencies.
-
Renewal initiatives.
While renewal initiatives such as La Relève are seen by central
agencies as an opportunity to tackle persistent and emerging human resource issues,
they are received with cynicism by officials in some departments still struggling with
downsizing issues - partly because human resource issues, such as the need for
renewal and rejuvenation, have been made worse by the implementation of Program
Review decisions. Furthermore many departments had not integrated such issues in
their expenditure reduction plans, or made allowance for addressing them.