Exhibit 2.1—Key milestones were not met—text version

2014 Spring Report of the Auditor General of Canada

Spring 2014 Report—Chapter 2

Exhibit 2.1—Key milestones were not met

This timeline shows the initial and actual key milestone dates for the request for information (RFI) and the request for proposals (RFP).

Activity Initial timeline Actual timeline
Release of the RFI March 2008 7 August 2008
Industry response to RFI April 2008 22 September 2008
Release of the RFP September 2008 29 April 2009
RFP closes November 2008 22 June 2009
Evaluation completed January 2009 13 July 2009
Contract awarded June 2009 14 August 2009
Service commences under the new contract 1 December 2009
(six-month transition period from contract award)
1 December 2009
(three-month transition period from contract award)
Source: Adapted from Public Works and Government Services Canada documents.